A hydrostatic pipe testing machine is selected for more than its ability to fill a pipe and apply pressure. The project also has to define the test requirement the equipment must follow and the record that will show each pipe was tested to it.
For an ERW tube mill line, these requirements should be agreed before the test system is specified. They determine which settings are controlled, which data is retained and how pipes that fail are handled.
This guide covers that planning work. For equipment types, operating modes and published features, see SRET’s hydrostatic tester.

Test pressure and hold time should come from the applicable product standard, customer specification or code requirement. They should not be treated as general machine settings.
SRET describes testing as filling the pipe with liquid until a specific pressure is reached, then holding that pressure for a specific time to check for leaks. The test pressure may exceed the designed working pressure, depending on the applicable regulation or code.
| Requirement | Information to Confirm |
| Governing requirement | API, AWWA or another agreed specification |
| Pipe grade | Material grade and any grade-specific condition |
| Pipe size | Outside diameter, wall thickness and length |
| Test pressure | Value or method used to determine it |
| Hold time | Required duration for each product group |
| Acceptance | What counts as a pass or a failure |
Quote the standard and product group rather than a pressure figure alone. The same machine may be used with several requirements, and each needs its own documented basis.
Reaching a set pressure and holding it steadily are different requirements.
The product page highlights stable test pressure, adjustable hold time, continuous pressure control during the hold period and specially designed intensifiers for stability during hold. Treat these as design features to be confirmed for the selected configuration, not as a pressure-accuracy guarantee.
Ask the supplier to state the conditions under which any pressure-control claim applies, including pipe size, product group and test mode.
SRET states that the machine can be set up so that pipe length, grade and working-pressure settings are entered at the operator control station without physical adjustments. It also states that testers can be designed for different end conditions, outside-diameter variations, pipe-length variations, grade and pressure requirements.
For planning, confirm which settings are entered electronically and which, if any, require mechanical changeover on the supplied machine.
Do not describe a changeover as adjustment-free until the supplier has confirmed it for the product range in the proposal.
The landing page says hydrostatic testers can be designed for fully automatic, semi-automatic and manual operation. The mode should be chosen against the production plan and the operator’s responsibilities, not just against throughput.
| Mode | Planning Question |
| Fully automatic | Which steps run without operator action, and how are interruptions handled? |
| Semi-automatic | Which actions need operator confirmation or manual operation? |
| Manual | Which tasks are manual, and which safety procedures apply? |
Each mode should have a written operating description. A single phrase such as “automatic testing” does not define the operator’s role.
The product page says the tester can automatically collect test information, generate a pressure-time curve and save it in a database for retrieval or printing. It also says data can be sent through PLC and network to other parts of the finishing floor.
Decide in advance which records the project needs and where they will be kept.
A recorded curve is only useful if it can be linked to the pipe it describes. Confirm how pipe identity travels through the line to the test record.
A pipe may fail because of a leak, a pressure drop or another condition defined in the acceptance requirement. The project should write down what happens next.
The tester’s value is in the accuracy of the decision and its record. Make that part of the acceptance scope rather than leaving it to local practice.
Hydrostatic testing sits among other finishing operations. The product page lists the pipe straightening machine, end facing machine and automatic packaging machine as related products.
Document the information the tester needs from upstream equipment and what it passes downstream.
For the end-condition requirements specifically, see our guide to end facing machine requirements before hydrostatic testing.
SRET describes single- and multi-head machines, multiple sealing-device options for in-line mill application, quick tooling changeover and fast test-pressure build time. These describe available design directions, not a fixed throughput for every pipe size.
Ask the supplier to state the product, test pressure, hold time and operating mode behind any capacity figure. Include the time needed for pipe loading, sealing, filling, pressurizing, holding, pressure release and discharge in the cycle definition.
When comparing proposals, use the same test requirement and product list. Otherwise differences in pressure or hold time may be mistaken for differences in machine performance.
| Category | Information to Provide |
| Products | Diameter, wall thickness, length, grade |
| Standard | Governing specification for each product group |
| Test condition | Pressure, hold time and acceptance rule |
| Operating mode | Fully automatic, semi-automatic or manual |
| Data | Required records, storage and transfer |
| Rejected pipes | Identification, removal and retest procedure |
| Line interface | Incoming condition and downstream release |
| Acceptance | Demonstration pipes, records and approvals |
A hydrostatic pipe testing machine is easiest to specify when the test requirement, record requirement and rejection procedure are written down first.
The product page then supplies the equipment options, while the project specification records the conditions each pipe must meet and the evidence that it did. That approach suits an ERW tube mill project more reliably than a general description of the testing sequence.